§ 51.57. How does a concessioner request arbitration of the construction cost of a capital improvement?
81 words·~1 min read·
/us/cfr/t36/s§ 51.57·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
If a concessioner requests arbitration of the construction cost of a capital improvement determined by the Director, the request must be made in writing to the Director within 3 months of the date of the Director's determination of construction cost under § 51.56. The arbitration procedures are described in § 51.51. The decision of the arbitration panel as to the construction cost of the capital improvement will be binding on the concessioner and the Director. \[66 FR 35083, July 3, 2001\]